
The Direct Answer: When is a Retainage Lien Timely?
Under the version of the Texas Property Code applicable to contracts signed before January 1, 2022, a subcontractor must file a lien affidavit for statutory retainage within 30 days of the date the original contractor abandons the project. Furthermore, notice of a claim for contractual retainage must generally state the existence of a requirement for retainage and be delivered within 30 days of abandonment or termination.
The Specificity Requirement for Contractual Retainage Notice
The dispute in IDP TM Properties centered on whether a subcontractor, Select Excavation, provided adequate notice of its contractual retainage claim under Section 53.057. Following the general contractor’s abandonment on December 2, 2022, the subcontractor sent an email on December 5 listing “total amounts owed” with payment applications attached.
The court held this was insufficient. Even though the attached payment applications contained a “retainage” line item, the email itself only referenced unpaid work amounts. The court emphasized that the notice must explicitly state the existence of a requirement for retainage to satisfy Section 53.057. Attorneys should note that providing notice of unpaid “work and materials” does not substitute for the specific notice required for “contractual retainage”.
Statutory Retainage and the Abandonment Clock
Regarding statutory retainage, the subcontractor argued it was entitled to a longer filing window under the Section 53.057(f) exception. This exception can extend the filing deadline to the 40th day after termination if the owner fails to provide notice of the abandonment.
However, the court ruled that the owner’s duty to notify subcontractors under Section 53.107 is only triggered if the subcontractor sent a formal notice of a claim before the abandonment occurred. Because Select Excavation had not provided any such pre-abandonment notice, the owner had no obligation to alert the subcontractor that the general contractor had walked off the job. Consequently, the subcontractor was bound by the strict 30-day deadline in Section 53.103, which it missed.
Procedural Trap: The “Trial by Consent” Doctrine
Perhaps the most vital lesson for trial lawyers in this opinion involves the waiver of conditions precedent. The subcontractor argued that the owner waived any challenge to the timeliness of the lien notice because the owner filed a general denial rather than a specific denial under Texas Rule of Civil Procedure 54.
The court disagreed, finding the issue was “tried by consent”. Because both parties submitted substantive evidence and briefing regarding the timeliness of the notice during the summary judgment proceedings without objection, any defect in the owner’s pleadings was cured. This serves as a reminder that active participation in summary judgment arguments on an unpleaded defense may waive a Rule 54 objection.
Practice Points for Construction Litigators
- Audit Your Notice Forms: Ensure all subcontractor notices for contractual retainage explicitly use the word “retainage” in the body of the notice.
- The 30-Day Hard Stop: In abandonment scenarios, assume the 30-day deadline for statutory retainage applies unless you can prove a pre-abandonment notice was sent to the owner.
- Rule 54 Vigilance: If an opposing party fails to specifically deny conditions precedent, object to the introduction of any evidence or briefing that challenges those conditions at the earliest possible moment to avoid a “trial by consent” finding.
Contact our Houston construction defect attorney today for assistance.
